A new Part 135 certificate is a project with five FAA phases. Most of the labor falls on the applicant:
Define the proposed operation.
Prepare the operations, maintenance, and training manuals.
Show compliance with FAA regulations and guidance.
Hire, train, and qualify flight crew and maintenance personnel.
Complete the FAA approval tasks.
Five phases and three gates. A gate is a go/no-go point: every item in the phase must be complete before the project continues.
| Phase | FAA Phase | Applicant / FAA Activity | Gate |
|---|---|---|---|
| 1 | Pre-application | Define the proposed operation, begin the application, and meet with the FAA certification team. | Gate 1 |
| 2 | Formal Application | Submit the application package, manuals, training curricula, compliance statement, management qualifications, proposed OpSpecs, and applicable Element Design (ED) DCTs. | Gate 2 |
| 3 | Design Assessment | FAA evaluates the manuals, programs, procedures, and supporting compliance evidence. | – |
| 4 | Performance Assessment | Demonstrate that the aircraft, personnel, training, procedures, and operating systems work as designed. | Gate 3 |
| 5 | Administrative Functions | FAA completes the certification record and issues the certificate and Operations Specifications. | Certificate issued |
Beginning September 30, 2026, new Part 135 applications are submitted through the FAA's Aviation Integrated Safety (AIS) Services, which replaces the Safety Assurance System (SAS). Some FAA material still refers to SAS.
| Manuals and Training | Design Compliance / DCTs |
|---|---|
|
|
|
A Data Collection Tool (DCT) is a group of related FAA compliance questions. The applicable DCTs depend on the proposed operation.
| Organizational Management | Flight Operations | Operations Management |
|---|---|---|
|
|
|
|
| Technical Operations | Onboard Operations | Ground Operations |
|
|
|
|
76 DCTs |
1,324 Compliance Questions |
Typical scope. The actual set depends on the aircraft and authorizations requested.
| DCT Example | Questions | Relative Size |
|---|---|---|
| Recent Experience | 9 | |
| Manual Management | 16 | |
| Training of Flight Crewmembers | 35 | |
| Airman Duties / Flight Deck Procedures | 69 |
Acquire an Existing Company: Key elements exist. The manuals, programs, and compliance work are FAA approved or accepted. The work narrows to qualifying the buyer's personnel and adding the buyer's aircraft, with experienced USAC specialists supporting the transition. In a well-prepared acquisition, the goal is to have the buyer operating in approximately 3 to 6 months, subject to FAA availability, aircraft readiness, and completion of required transition work.